These 10 free CSI-HQS questions are organized by exam domain, so you can see how each part of the Certified Specialist of Inspection - Housing Quality Standards blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Inspecting housing choice voucher units.

Question 1

An inspector using HUD-52580-A records these electrical features: living room-one duplex receptacle and a floor lamp; kitchen-one receptacle and a permanent ceiling light; bedroom-two separate wall outlets; bathroom-a permanent ceiling light. All listed equipment works safely, and no other outlets or light fixtures are present. Which room falls short of the electrical minimum?

Show answer & explanation

Correct answer: B - Living room

Question 2

All required smoke alarms in a voucher unit sound when tested during an October 2026 inspection. Their locations are correct, but each is powered only by a replaceable 9-volt battery. The owner promises annual battery changes and notes that the PHA still uses HQS. The inspector should explain that:

Show answer & explanation

Correct answer: D - Hardwired alarms or alarms with sealed 10-year batteries are required.

Question 3

A gas water heater has been replaced with an electric model in a unit subject to legacy HQS. The wiring is safe, hot water is available, and the old combustion flue has been removed. A working temperature-pressure relief valve is installed, but its discharge opening has no pipe attached. Which correction remains necessary?

Show answer & explanation

Correct answer: C - Add a correctly directed discharge line; no combustion flue is needed.

Question 4

A lead-clearance report dated October 2026 records no visible dust or debris after paint stabilization in a tenant-based voucher unit. Single-surface dust-wipe results are: floor, 8 µg/ft²; interior window sill, 25 µg/ft²; window trough, 70 µg/ft². Under HUD's federal clearance requirements, how should these results be handled?

Show answer & explanation

Correct answer: B - Reclean and retest the floor area represented by its sample.

Question 5

"The resident agreed to it," an owner tells an inspector applying legacy HQS. The owner supplied a working microwave in place of an oven and range but still furnishes ovens and ranges to unassisted tenants in the same building. Which explanation correctly applies the cooking-equipment exception?

Show answer & explanation

Correct answer: A - Reject it; unassisted tenants in the building still receive owner-supplied ovens and ranges.

Domain 2: Conducting pre-inspection and inspection preparations and procedures.

Question 6

Electricity is off at a voucher unit scheduled for inspection. The owner says the family failed to pay its bill; the family says electricity is included in rent. Before assigning responsibility for the interruption, where should the inspector look for the controlling allocation?

Show answer & explanation

Correct answer: A - The executed lease and HAP contract, including approved changes to the utility allocation.

Question 7

On entering an occupied voucher unit, an inspector detects a strong gas odor near the boiler. The owner offers to have a contractor come the next morning. What takes priority over completing the inspection?

Show answer & explanation

Correct answer: A - Direct occupants outside, then call 911 and the gas utility from a safe location.

Domain 3: Negotiation and arbitration with landlords and residents.

Question 8

A resident with a documented mobility disability calls to request that routine inspections take place after 2 p.m. She says the change is disability-related, but neither the conversation nor the PHA's records explain why the time matters. What additional information may the PHA seek when considering this oral request?

Show answer & explanation

Correct answer: D - A limited explanation of the disability-related need for afternoon inspections, without re-verifying the documented disability.

Domain 4: Understanding the need for consistency and re-inspections.

Question 9

Before the repair deadline, an owner submits dated, unit-identifiable photographs and video of a required exit after an obstructing cabinet was removed. The video shows the exit opening fully, and the resident confirms the repair. This was the unit's only failure. The PHA allows this verification method and finds the evidence conclusive. Must an inspector return before closing the finding?

Show answer & explanation

Correct answer: C - No; document the verified correction and close the finding using the conclusive evidence.

Domain 5: Determining the impact inspection outcomes have on their agency’s SEMAP score.

Question 10

An inspection dashboard shows that 87% of units already under HAP passed their periodic HQS inspection on the first visit. The director takes this as evidence of satisfactory SEMAP performance for HQS enforcement. Which file review would actually test that conclusion?

Show answer & explanation

Correct answer: C - Whether failed units had timely verified repairs or required enforcement when repair deadlines were missed.

That's 10 of 1,030